Manor Park, Newbury

Client: David Wilson Homes

Role: Expert Opinion

Project Value: £10million

Dates: January  2012

Location: London, UK

“The terms of settlement have been agreed in respect of our client’s claim. We would like to thank Mr Carolan for his assistance in achieving this result for our client”.

Project Issues

David Wilson Homes wanted to claim for the costs incurred when a land slip took place at the rear of their new development; Manor Park Newbury. Advice provided by the defendant Engineer regarding land embankment and drainage design failed to include land drainage at the top of the embankment. This lack of information and heavy rainfall resulted in remedial work required to complete the works and therefore increased costs and time to our client.

Our Approach

Lindford Consulting was instructed by the Instructing solicitor to produce a Quantum Expert Report, initially for the purposes of a Pre-action Protocol and if no resolution was sought; formal proceeding. Having received the factual information arising out of the claim, Edward Carolan (appointed Expert) prepared a detailed analysis of the remedial work, including quantifying the amount of work undertaken and subsequently valuing the works. Following the Quantum analysis Edward produced a Quantum Expert Report of the findings and his quantum assessment of the value of the remedial work.

The Outcome

Following the submission of the Expert Report, further negotiations took place between the parties and an amicable settlement was reached. The rigorous method of quantifying and valuing the remedial works, together with Edwards’s independent and impartial approach ensured a very satisfactory outcome for our client.

Quick Enquiry

    Your Name

    Your Email

    Your Message

    News & Case Studies

    Stop Leaving Money On The Table (Part 3): Your Step-by-Step Guide to Getting Paid

    Stop Leaving Money On The Table (Part 3): Your Step-by-Step Guide to Getting Paid

    Variation disputes are one of the most common (and costly) issues in construction projects. Misunderstandings around...

    3 Jul 2025
    Stop Leaving Money On The Table (Part 2): How to Value and Secure Payment for Variations

    Stop Leaving Money On The Table (Part 2): How to Value and Secure Payment for Variations

    Your Systematic Approach to Variation Valuation Once entitlement is established, understanding the contractual principles and mechanisms...

    25 Jun 2025

    Sign up to our Newsletter